Germany's national register showed 1,529,612 plug-in solar systems operating at the end of September 2026, up from about 69,000 commissioned in 2022. Growth came after the 2024 Solarpaket raised the inverter limit to 800 VA, dropped the need to tell the network operator and simplified registration. WA's draft standard is based on Germany's DIN VDE V 0126-95, with local changes and an added battery section.
On this page (6 sections)
Germans call them Balkonkraftwerke, “balcony power stations”, and the official term is Steckersolargeräte, plug-in solar devices. Germany is the model WA chose: the draft WA standard is built on the German product standard, and the government’s case for the change leans on the fact that, in Energy Minister Amber-Jade Sanderson’s words, “Millions of European households already use these systems every day.”
How many balcony systems does Germany have?
About 1.5 million registered, and probably more in reality. The Bundesnetzagentur, Germany’s federal network agency, runs the national register of generators (the Marktstammdatenregister, or MaStR). Its statistics, using register data as at 13 October 2026, show:
| Year commissioned | Plug-in systems | Panel capacity |
|---|---|---|
| 2022 | 69,205 | 48.4 MW |
| 2023 | 287,645 | 222.9 MW |
| 2024 | 446,393 | 440.0 MW |
| 2025 | 438,098 | 541.7 MW |
| January to September 2026 | 327,044 | 456.5 MW |
| Operating at end of September 2026 | 1,529,612 | 1,671.2 MW |
These numbers move. Owners have one month to register, and late registrations push recent figures up. That is why the agency’s own press releases gave smaller early figures: about 260,000 for 2023, about 435,000 for 2024 and about 430,000 for 2025, each published in the January after the year ended.
The register also undercounts. In its January 2025 release, the Bundesnetzagentur said it assumes the true number is higher, “da vermutlich nicht alle Balkonanlagen registriert sind” (because probably not all balcony systems are registered). Nobody knows the real total. The ABC’s description of about one in ten German households having a system is an estimate, not a register count.
Is the German boom still growing?
The count is still rising, but yearly additions have levelled off. By the agency’s table, 2025 came in slightly below 2024 by number of systems, though higher by capacity, because newer kits carry more panel power. One MaStR-based analysis by the consumer site EnergieMagazin found January to July 2026 also ran below the same months of 2025. That is a secondary analysis, not an official statement.
What was the 800 W rule, and what changed in 2024?
The big change was the Solarpaket, which took effect on 16 May 2024. The Bundesnetzagentur’s balcony solar page and the federal energy ministry’s March 2026 fact sheet set out the rules for systems first commissioned since then:
- Inverter output is capped at 800 VA in total. The ministry says the limit was raised (“angehoben”) to that level.
- Panels can total up to 2,000 W.
- There is no longer any duty to notify the network operator. A short registration in the MaStR is enough, and the network operator gets the data automatically.
- Old spinning-disc meters that can run backwards are tolerated for a while, until the meter operator checks or replaces them, which the agency says should take weeks or at most a few months.
- Surplus power that flows to the grid is not paid for, which the ministry calls “unentgeltliche Abnahme” (taking it without payment).
Registration had already been simplified from 1 April 2024. The agency’s March 2024 release says owners now enter only five details about their device, plus their personal details, where previously “Vorher waren es rund 20 Angaben” (before, it was around 20 details). The ministry’s fact sheet adds that plug-in solar devices have been exempt from VAT since 2023.
What about German renters and apartment owners?
They got a legal right to ask. A law published on 16 October 2024 and in force from 17 October 2024 made plug-in solar a “privileged” change in both tenancy law and apartment ownership law. Under § 554 of the German Civil Code, a tenant can require the landlord to allow changes that serve “der Stromerzeugung durch Steckersolargeräte” (electricity generation by plug-in solar devices). The claim only fails if the change cannot reasonably be expected of the landlord, even after weighing the tenant’s interests.
The ministry sums it up: tenants and apartment owners still need consent, but landlords and owners’ associations can only refuse “in begründeten Ausnahmefällen” (in justified exceptional cases). WA has no equivalent rule. See renters and apartments.
What is DIN VDE V 0126-95?
It is the German product standard for plug-in solar devices, published in December 2025. The VDE, which publishes it, announced it on 14 November 2025 as the world’s first product standard for these devices. The “V” marks it as a pre-standard (Vornorm). Its key points, from the VDE release:
- The inverter can feed in at most 800 VA.
- With an ordinary household plug, panels are limited to 960 W (800 W plus 20%).
- With a special energy plug and socket, panels can go up to 2,000 W.
- Devices with batteries are outside its scope. The committee responsible has started planning a separate part for them.
What did WA copy from Germany?
The core of it. The consultation paper says WA has tried “As much as possible” to align its draft with DIN VDE V 0126-95, “to take advantage of work already done for more mature overseas markets”. The draft standard says the two are as similar as possible, but the WA version takes priority where they differ.
| Feature | Germany | WA draft |
|---|---|---|
| Inverter limit | 800 VA | 800 VA |
| Panel limit | 2,000 W (960 W on an ordinary household plug) | 2 kW DC combined solar and battery |
| Plug | German household plug or special energy plug | Australian Type I plug (AS/NZS 3112) |
| Batteries | Not covered by the standard yet | Allowed, LFP or sodium-ion, DC-coupled |
| Alongside rooftop solar | Allowed, according to the ministry’s fact sheet | Not allowed at a site with a fixed installation |
| Tell the network | Register in MaStR only | Install, then notify Western Power or Horizon Power |
| Export payments | None under the plug-in rules | None for now |
| Wind loading | Not covered in the VDE release | Mount type tests up to wind region B |
| Tenant rights | Legal claim to permission since October 2024 | No change to tenancy law |
The WA panel limit row is my reading. I could not find a lower panel limit tied to the ordinary plug in the WA draft, unlike Germany’s 960 W.
The paper lists the main local changes as wind loading, inverter grid codes (WA uses AS/NZS 4777.2) and the extra battery section. The rules page sets out the WA draft in full, and the UK guide shows a different approach to the same idea.
Sources for this page
- Statistik zur Stromerzeugungsleistung erneuerbarer Energieträger, September 2026 (data as at 13 October 2026), Bundesnetzagentur
- Balkon-Solaranlagen, Bundesnetzagentur
- Bundesnetzagentur vereinfacht die Registrierung von Balkonkraftwerken, press release, 28 March 2024
- Zubau Erneuerbarer Energien 2023, Bundesnetzagentur press release, 5 January 2024
- Ausbau Erneuerbarer Energien 2024, Bundesnetzagentur press release, 8 January 2025
- Ausbau Erneuerbarer Energien 2025, Bundesnetzagentur press release, 8 January 2026
- Balkonkraftwerk Marktstudie 2026 (MaStR export of 3 September 2026), EnergieMagazin
- Western Australia set to lift ban on balcony solar in national first, ABC News, 28 October 2026
- Kurzinformation zu Steckersolargeräten, German Federal Ministry for Economic Affairs and Energy, March 2026
- Weltweit erste Produktnorm für Steckersolargeräte, VDE press release, 14 November 2025
- § 554 BGB, Gesetze im Internet (German Federal Ministry of Justice)